October 22, 2007: Inaugurated was the 79.818-kilometer road stretching from San Andres to Viga and five (5) bridges, which are components of the fourth phase of the Arterial Road Links Development Project.
Total project cost amounted to approximately 1.1 billion pesos and was financed by Official Development Assistance from the Government of Japan. This road section is the biggest in the planned 200-kilometer Catanduanes Circumferential Road Improvement Project.
Target Completion: 2010
RELATED LINKS:
Pagsangahan bridge |
- CP I: Codon-San Andres-Virac-Viga Road (79.848 kms.) - completed
- CP II: Viga-Bagamanoc Road (9.985 kms.) - in progress
- CP III: Bagamanoc-Pandan Road (48.106 kms.) - in progress
- CP IV: Pandan-Caramoran-Codon (62.221 kms.) - in progress
Target Completion: 2010